当前货币:HKD

您的购物车中没有商品。

NEC Managing Reality

NEC Managing Reality A Practical Guide To Applying NEC3, 2nd edition (5 book set)

  • 作者:
  • ISBN: 9780727757166
  • 出版时间 October 2012
  • 规格: Paperback (5 volumes) , 630 pages
  • 适应领域: International ? 免责申明:
    Countri(es) stated herein are used as reference only
最新版已經出版!
  • 描述 
  • 大纲 
  • 作者 
  • 详细

    Managing Reality is a series of books written by NEC experts well versed in using NEC3 in industry that explains how NEC3 can be used to optimum benefit in everyday environments. Ultimately, this suite of books forms the complete and authoritative guide to getting the most from NEC3 for your projects.

    The books are based on usage of the NEC’s core document – theEngineering and Construction Contract – although the principles and procedures they discuss apply equally across all the documents in the NEC suite.

    Managing Reality, 2nd edition, places great emphasis on offering ‘practical tips’ at appropriate points in the text and highlighted examples. Standard forms are included with their usage explained together with checklists.Managing Reality, 2nd edition, are practical manuals designed to aid both existing and new users in implementing the NEC, vital for anyone involved in preparing, administering or contributing to a NEC contract.

  • Contents:

     

    BOOK 1: Introduction to the Engineering and Construction Contract

    Preface 
    Foreword

    Introduction to the Engineering and Construction Contract, concepts and terminology

    1.1 Introduction
    1.2 What is the ECC?
    ICE Conditions of Contract Withdraw
    1.3 Why is the ECC different?
    1.4 ECC structure
    1.5 Conventions 
    1.6 Concepts 
    1.7 Terminology 
    1.8 Terminology not used in the ECC 
    1.9 Commentary on other aspects of the ECC 
    1.10 How does the ECC affect the way you work? 
    1.11 Summarising the ECC 
    1.12 Potential benefits

    Roles in the Engineering and Construction Contract

    2.1 Introduction
    2.2 Roles in the ECC
    2.3 How to designate a role
    2.4 Separation of roles and responsibilities
    2.5 Other roles in the ECC
    2.6 The project team 
    2.7 What does the ECC mean to me
    2.8 Delegation 
    2.9 Replacement of personnel

    Appendix: List of duties
    Index


    BOOK 2: Procuring an Engineering and Construction Contract

    Preface 
    Foreword

    Procurement

    1.1 What is procurement? 
    1.2 Value for money
    1.3 The procurement process
    1.4 Procurement time cycle
    1.5 Procurement strategy
    1.6 Contract strategy
    1.7 Public sector procurement 
    1.8 Generic good principles for effective procurement 
    1.9 Long-term agreements 
    1.10 How does the ECC contribute to effective ‘partnership’? 
    1.11 ECC tendering procedure 
    1.12 From tendering to contract 
    1.13 Procurement scenarios

    Appendix: Assessing tenders

    A1.1 Introduction 
    A1.2 Information to include in the invitation to tender (ITT) 
    A1.3 Evaluation 
    A1.4 Conducting the evaluation

    Appendix: ECC tender documentation

    A2.1 Introduction 
    A2.2 Header page 
    A2.3 Letter of Invitation 
    A2.4 Conditions of Tendering 
    A2.5 Tender submission documents 
    A2.6 Contract documents

    Contract Options

    2.1 Introduction 
    2.2 ECC main and secondary Options – general 
    2.3 Main Options 
    2.4 Priced contracts 
    2.5 Target contracts 
    2.6 Cost-reimbursable contracts 
    2.7 Administering the ECC cost-based contract 
    2.8 Dispute resolution procedure Options in ECC3 
    2.9 Secondary Options

    Appendix: Audit Plan

    A3.1 Introduction
    A3.2 Basis of Audit Plan and procedures 
    A3.3 Main audit objectives 
    A3.4 Reporting 
    A3.5 Audit report 
    A3.6 Goals 
    A3.7 Amendments to Audit Plan
    A3.8 Distribution of Audit Plan
    B3.1 Audit objectives 
    B3.2 Procedures 
    B3.3 Audit records 
    C3.1 Audit objectives 
    C3.2 Audit records 
    C3.3 Information to be provided by the Project Team 
    D3.1 Audit objectives 
    D3.2 Procedures 
    D3.3 Audit records 
    D3.4 Information to be provided by the Project Team 
    E3.1 Audit objectives 
    E3.2 Procedures 
    E3.3 Audit records 
    E3.4 Information to be provided by the Project Team 
    F3.1 Audit Objectives 
    F3.2 Procedures 
    F3.3 Audit records 
    F3.4 Information to be provided by the Project Team 
    G3.1 Audit objectives 
    G3.2 Procedures 
    G3.3 Audit records 
    H3.1 Audit objectives 
    H3.2 Procedures 
    H3.3 Audit records 
    H3.4 Information to be provided by the Project Team

    Completing the Contract Data

    3.1 Introduction 
    3.2 Structure of the chapter 
    3.3 Part one of this chapter: choosing the main Option
    3.4 Part two of this chapter: choosing the secondary Options 
    3.5 Part three of this chapter: choosing optional Contract Data statements 
    3.6 Part four of this chapter: all entries in Contract Data part one by the Employer 
    3.7 Part five of this chapter: Contract Data part two by the Contractor

    Works Information guidelines

    4.1 Introduction 
    4.2 Providing the Works 
    4.3 What should be included in the Works Information 
    4.4 Separation of the Works Information and Site Information 
    4.5 Where the Works Information fits into the contract documents 
    4.6 Structuring the Works Information 
    4.7 Interface management 
    4.8 General rules in drafting the Works Information 
    4.9 Site Information

    Appendix: Works Information clauses

    A4.1 Works Information clauses


    BOOK 3: Managing the contract

    Preface 
    Foreword

    Payment procedures in the Engineering and Construction Contract

    1.1 Introduction
    1.2 Payment procedure
    1.3 How the ECC3 includes the HGCR Act 1996
    1.4 The effects of Y(UK)2 
    1.5 Payment procedure on Completion
    1.6 Payment procedure after Completion 
    1.7 Payment procedure after the defects date

    Control of Time

    2.1 Introduction 
    2.2 Terminology 
    2.3 What is the programme? 
    2.4 Definition of the Accepted Programme 
    2.5 The purpose of the Accepted Programme 
    2.6 What is included in the programme? 
    2.7 Submission of the first programme 
    2.8 How often is the programme revised? 
    2.9 Acceptance of the programme 
    2.10 Completion 
    2.11 Take over by the Employer 
    2.12 Acceleration 
    2.13 Other aspects of programming in the ECC

    Control of quality

    3.1 Introduction 
    3.2 The ECC and quality 
    3.3 The Contractor’s obligations 
    3.4 Role of the Employer’s representatives with respect to quality 
    3.5 Employer’s supply 
    3.6 Sub- contracting 
    3.7 Quality control 
    3.8 Defective work 
    3.9 Certification 
    3.10 Enforcement 
    3.11 NEC 3rd Edition

    Disputes and dispute resolution

    4.1 Introduction 
    4.2 How disputes arise 
    4.3 How the ECC seeks to reduce the incidence of disputes 
    4.4 Dispute resolution under the ECC 
    4.5 Adjudication – general comments and observations 
    4.6 NEC 3rd Edition


    BOOK 4: Managing Change

    Compensation events

    1.1 Introduction
    1.2 Compensation event procedure: background
    1.3 What is a compensation event?
    1.4 Where to find a list of compensation events
    1.4.1 Core compensation events
    1.4.2 Main Options B and D only
    1.4.3 Secondary Options X14, Y(UK)2 and X15
    1.4.4 Contract Data (part one)
    1.5 Roles of the Project Manager and Contractor
    1.6 Administering compensation events
    1.6.1 Changes to the Completion Date
    1.6.2 Changes to the Prices
    1.6.3 Procedure for change
    1.6.4 Cost of preparing for quotations
    1.7 Notification of a compensation event
    1.7.1 Proposed instruction or changed decision
    1.7.2 Notification by the Project Manager
    1.7.3 Notification by the Contractor
    1.7.4 The four-point test
    1.8 Quotations for compensation event
    1.8.1 Introduction
    1.8.2 When are quotations submitted?
    1.8.3 Instructions for quotations
    1.8.4 What is included in the quotation?
    1.8.5 Acceptance of a quotation
    1.9 Assessment of quotations
    1.9.1 Assessment by the Project Manager
    1.10 The use of the programme for the assessment of compensation events
    1.10.1 Programmes which accompany compensation events
    1.11 Implementation of compensation events
    1.12 Reduction of Prices
    1.13 Frequently asked questions
    1.13.1 Eight-week barrier
    1.13.2 Claims
    1.13.3 Project Manager does not notify
    1.13.4 Early warnings
    1.13.5 Grouping compensation events
    1.13.6 Amending the contract prior to execution
    1.13.7 Removing compensation events
    1.13.8 Adding compensation events
    1.13.9 The Project Manager fails to act
    1.14 Format of a compensation event quotation
    Appendix 1 Compensation event procedure

    Schedule of Cost Components

    2.1 Introduction
    2.2 What is the Schedule of Cost Components?
    2.3 Why has this approach been taken?
    2.4 Assessment options
    2.5 When is the Schedule of Cost Components used?
    2.5.1 Priced-based contracts – Options A and B contracts
    2.5.2 Cost-based contracts – Options C, D and E contracts
    2.5.3 Option F contracts
    2.5.4 SCC summary
    2.6 Defined Cost
    2.7 The Fee
    2.7.1 The Fee
    2.8 The components of cost included under the full Schedule of Cost Components
    2.8.1 Working Areas
    2.8.2 Cost component heading 1: People
    2.8.3 Cost component heading 2: Equipment
    2.8.4 Cost component heading 3: Plant and Materials
    2.8.5 Cost component heading 4: Charges
    2.8.6 Cost component heading 5: Manufacture and fabrication outside the Working Areas
    2.8.7 Cost component heading 6: Design outside the Working Areas
    2.8.8 Cost component heading 7: Insurance
    2.8A The components of cost included under the shorter Schedule of Cost Components (SSCC)
    2.9 Contract Data part two
    2.10 Putting it all together for payment – Option C
    2.11 Audits
    2.11.1 Compensation events
    2.11.2 Options C, D and E
    2.12 Use of the Shorter Schedule of Cost Components
    2.12.1 People
    2.12.2 Equipment
    2.13 Practical issues
    2.13.1 Working on multiple projects on the same site
    2.13.2 Example of the principles of the assessment of change
    2.13.3 Omissions
    2.13.4 Project Manager’s assessment
    2.13.5 Numerous small compensation events
    2.13.6 Issue of Site Information drawings
    2.13.7 Occasions when Defined Cost is not used
    2.14 Preliminaries and people costs
    2.14.1 Introduction

    Appendix 2 
    Section A: Based on the full Schedule of Cost Components
    Section B: Based on the shorter Schedule of Cost Components
    Section C: Based on rates and lump sums
    Appendix 3 Example people cost calculations
    Appendix 4 Comparison between traditional preliminaries build-up and how they relate to SCC and SSCC
    Appendix 5 Interrelationship between Contractor’s and Subcontractor’s share on target cost contracts

    Index


    BOOK 5: Managing Procedures

    Preface 
    Foreword

    ECC Management: Procedures

    1.1 Introduction
    1.2 Records to maintain
    1.3 Review meetings
    1.4 Contract administration
    1.5 Practical administration
    1.6 How to manage an ECC

  • Bronwyn Mitchell Bcom (Hons) BProc MBA MCIPS MCIArb has been involved with the NEC since 1995 and has drafted hundreds of contracts based on the NEC. She was also involved in drafting various documents which were used in developing formal NEC contracts and publications. Bronwyn acts as a trainer and consultant in the use of all NEC contracts.

    Barry Trebes FRICS BSc (Hons) MSc FAPM FInstCES is a Project Director with Mott MacDonald. Since 1983, his experience has ranged across a wide variety of projects including airport, rail, water, power and commercial developments and includes, most notably, the Stansted Airport development, the Heathrow Express Rail Link, CTRL, East London Line and a number of PFI/PPP contracts including the LUL PPP Contract. His first encounter with the NEC was in 1992 as senior commercial manager on the Heathrow Express Rail Link project working as a consultant for BAA plc (the earliest major user of NEC). Barry’s immense experience of NEC projects has led to him providing training and mentoring to clients, contractors and professional organisations throughout the industry. As Managing Director of Needlemans he initiated in 1998 the first ever web system named Contract Change Management (CCM) for the management of NEC contracts with MPS Limited. He is also co-author of BSI PD BS 6079 part 4 Project Management in the Construction Industry.

你可能需要

The Hong Kong Company Secretary's Handbook: Practice and Procedure (11th Edition)
The Hong Kong Company Secretary's Handbook: Practice and Procedure (11th Edition)

List Price: AU$101.65

AU$98.60 Save AU$3.05 (3%)

Hong Kong Tax & Accounting Practical Toolkit (Basic Package)
Hong Kong Tax & Accounting Practical Toolkit (Basic Package)
AU$691.41
Hong Kong Company Secretary Checklist, 2nd Edition
Hong Kong Company Secretary Checklist, 2nd Edition

List Price: AU$262.20

AU$254.33 Save AU$7.87 (3%)

Law of Companies in Hong Kong, 4th Edition (Hardcopy + e-Book)
Law of Companies in Hong Kong, 4th Edition (Hardcopy + e-Book)

List Price: AU$665.00

AU$645.05 Save AU$19.95 (3%)

Butterworths Hong Kong Discrimination Law Handbook, 4th Edition
Butterworths Hong Kong Discrimination Law Handbook, 4th Edition

List Price: AU$285.00

AU$276.45 Save AU$8.55 (3%)

Sentencing in Hong Kong, 11th Edition
Sentencing in Hong Kong, 11th Edition

List Price: AU$680.20

AU$659.79 Save AU$20.41 (3%)

Butterworths Hong Kong Company Law (Winding-Up and Miscellaneous Provisions) Handbook, 6th Edition
Butterworths Hong Kong Company Law (Winding-Up and Miscellaneous Provisions) Handbook, 6th Edition

List Price: AU$433.20

AU$420.20 Save AU$13.00 (3%)

Butterworths Hong Kong Company Law Handbook, 26th Edition
Butterworths Hong Kong Company Law Handbook, 26th Edition

List Price: AU$836.00

AU$810.92 Save AU$25.08 (3%)

Cross-Border Crime in Hong Kong: Extradition, Mutual Assistance & Financial Sanctions, 3rd Edition
Cross-Border Crime in Hong Kong: Extradition, Mutual Assistance & Financial Sanctions, 3rd Edition

List Price: AU$395.20

AU$383.34 Save AU$11.86 (3%)

Clough & Clough on Personal Injuries
Clough & Clough on Personal Injuries

List Price: AU$285.00

AU$276.45 Save AU$8.55 (3%)

Hong Kong Personal Insolvency Manual, 3rd Edition
Hong Kong Personal Insolvency Manual, 3rd Edition

List Price: AU$380.00

AU$368.60 Save AU$11.40 (3%)

Butterworths Hong Kong Conveyancing and Property Law Handbook, 6th Edition
Butterworths Hong Kong Conveyancing and Property Law Handbook, 6th Edition

List Price: AU$342.00

AU$331.74 Save AU$10.26 (3%)

A Practical Guide to Resolving Shareholder Disputes, 2nd Edition
A Practical Guide to Resolving Shareholder Disputes, 2nd Edition

List Price: AU$342.00

AU$331.74 Save AU$10.26 (3%)

Tort Law in Hong Kong, 5th Edition (Hardcopy + ebook)
Tort Law in Hong Kong, 5th Edition (Hardcopy + ebook)

List Price: AU$475.00

AU$460.75 Save AU$14.25 (3%)

Company Law in Hong Kong: Practice and Procedure 2023 (Hardcopy + e-Book)
Company Law in Hong Kong: Practice and Procedure 2023 (Hardcopy + e-Book)

List Price: AU$607.62

AU$589.39 Save AU$18.23 (3%)

Company Law in Hong Kong: Insolvency 2023 (Hardcopy + e-Book)
Company Law in Hong Kong: Insolvency 2023 (Hardcopy + e-Book)

List Price: AU$540.17

AU$523.96 Save AU$16.21 (3%)

Hong Kong Company Law, 15th Edition
Hong Kong Company Law, 15th Edition

List Price: AU$93.48

AU$90.68 Save AU$2.80 (3%)

Private Equity in Hong Kong and China, 4th Edition
Private Equity in Hong Kong and China, 4th Edition

List Price: AU$380.00

AU$368.60 Save AU$11.40 (3%)

Brooke's Notary Hong Kong, 3rd Edition
Brooke's Notary Hong Kong, 3rd Edition

List Price: AU$323.00

AU$313.31 Save AU$9.69 (3%)

Butterworths Hong Kong Employees' Compensation Handbook, 7th Edition
Butterworths Hong Kong Employees' Compensation Handbook, 7th Edition

List Price: AU$399.00

AU$387.03 Save AU$11.97 (3%)